Estimated Schedule

RFP date of issue - 16th May 2014

RFP collection date - 18th July 2014

RFP submission date - 17th October 2014

Shortlisting of proponents - 21st November 2014

Negotiations with proponents - 5th December 2014

Finalisation of negotiations - 12th December 2014

Process

Clarification questions from Proponents closed on 12th September 2014. The Privatisation Unit is obliged to reply to the clarification questions by 10th October 2014.

The deadline date for the submissions of RFP proposals by Proponents is 17th October 2014.

One submission has been received.

A Marine Technical Sub-Committee and a Finance Technical Sub-Committee have been constituted under the authority of the Evaluation and Adjudication Committee (EAC) to draw up and submit their respective technical reports to the EAC.

These two sub-committees have concluded their assignments.

The Evaluation and Adjudication Committee (EAC) has submitted its final report. 

Current Status

  • The PU has commenced preliminary negotiations with Proponent.
  • These negotiations are deemed to be of a complex nature and therefore are foreseen to take a substantial​ duration for them to be finalised.